Bangor airs August paving schedule

The 2005 paving program for the city of Bangor for the week of Aug. 15 is as follows: Monday, Norway Road one side of road, Carver St. entire;

Wednesday, Finson Road – Davis Road to the bridge; Thursday, Finson Road – Davis Road to the bridge; Friday, Finson Road – Davis Road to the bridge.

Paving for the week of Aug. 22 is as follows: Monday, Finson Road – Davis Road to the bridge; Tuesday, Finson Road – Davis Road to the bridge; Thursday, Norway Road – Webster to Carver, Norway Road – Carver, entire Carver Street, Friday, Linden Street – Nowell to Fountain, Madison Street – Center to Kenduskeag.

Inclement weather may require adjustment of this schedule on a day to day basis.