Dec. 3, 2003 – Groundbreaking
April 2004 – Prospect foundation complete
June 2004 – Verona foundation complete
November 2004 – Prospect and Verona lower pylons completed to deck height
Dec. 22, 2005 – Verona upper pylons completed
April 26, 2006 – Prospect upper pylons completed
July 27, 2006 – Verona back span meets land
Aug. 10, 2006 – Prospect back span meets land
Sept. 7, 2006 – Final observatory ring beam placement
Sept. 14, 2006 – Bridge deck meets in the middle
Sept. 29, 2006 – Prospect roof placed
October 2006 – Verona roof placed
November 2006 – Observatory completed
December 2006 – Bridge opened to traffic
SOURCE: Maine Department of Transportation