This week’s aggressive construction schedule includes work on I-95 as well as on-and-off ramps in Bangor. There will also be construction activity, not related to MaineDOT’s work, on Stillwater Avenue this week.
Tuesday, Sept. 25
Beginning at 8 p.m., the Union Street offramp will be closed for paving. When paving on the offramp is completed that night, it will be reopened and the Union Street onramp will be closed for paving. It is expected that both the onramps and offramps will be fully opened by 5:30 a.m. on Wednesday.
Travel will be restricted to one lane on I-95 northbound from Union Street to the area of the Broadway overpass during the evening hours. This lane restriction is expected to continue until Friday.
Wednesday, Sept. 26
Beginning at 8 p.m., the Hammond Street offramp will be closed. When work on the offramp is completed that night, it will be reopened and the Hammond Street onramp will be closed. It is expected that both the on and off ramps will be fully opened by 5:30 a.m. on Thursday.
Thursday, Sept. 27
Beginning at 8 p.m., the Hammond Street offramp will be closed for paving. When paving on the offramp is completed that night, it will be reopened and the Hammond Street onramp will be closed for paving. It is expected that both the onramps and offramps will be fully opened by 5:30 a.m. on Friday.
Friday, Sept. 28
Complete the northbound lane restriction work on I-95 from Union Street to Broadway. Crews continue lane restrictions on I-95 northbound and southbound by the Broadway overpass.