The ongoing work on the Broadway overpass in Bangor, both north- and southbound, continues throughout the week. The construction activity listed below is highway work being done in addition to the work on the overpass.
Monday, 10/1/07
Finish work on the northbound travel lane of the Broadway overpass on I-95.
Open this lane and set up a new closure in the passing lane of I-95 beginning at Hammond Street and extending through the Broadway overpass.
Tuesday, 10/2/07
Continue work in the passing lane from Hammond Street to the Broadway overpass.
Wednesday, 10/3/07
Continue work in the passing lane from Hammond Street to the Broadway overpass.
Thursday, 10/4/07
Finish work in the passing lane from Hammond Street to the Broadway overpass by Friday morning.
Friday, 10/5/07
Remove passing lane closure from Hammond Street to Broadway overpass and close the passing lane from Broadway to Hogan Road.
Saturday, 10/6/07
Continue work on I-95 in the passing lane from Broadway to Hogan Road.
Sunday, 10/7/07
Continue work on I-95 in the passing lane from Broadway to Hogan Road.