November 08, 2024
Archive

Temporary bridge completed in Abbot

ABBOT – Construction is complete on a temporary bridge that failed a week and a half ago in this southern Piscataquis County town.

Replacement beams were installed, and deck planks and bridge railings were restored on the bridge, which carries traffic on Routes 6, 15 and 16.

The project was finished late Tuesday.

The new temporary bridge carries several critical restrictions. The bridge is posted against carrying more than one truck at a time; trucks approaching the bridge from the south must stop before crossing; and all traffic on the bridge will be reduced to 15 mph.


Have feedback? Want to know more? Send us ideas for follow-up stories.

comments for this post are closed

You may also like